Site Works Update – W/C 1st April 2019

Soil-fix continuing works south of the Cala Homes site and making good progress.   Scofell will be working along Minorca road to remove a few trees to allow for the temporary footpath to be constructed.   The Maultway road improvements is ongoing and making good progress and the traffic management has changed slightly. Please allow…

Details

Site Works Update – W/C 18th March 2019

Tree and vegetation clearance has commenced at Frith Hill near Alphington road.   Soil-fix working south of the M1 parcel, between the Basingstoke canal and the Cala plot.   The Maultway road upgrade is progressing well. The traffic phasing has changed to allow for the remaining part of the roundabout to be constructed.   Mindenhurst…

Details

Site Works Update – W/C 11th March 2019

Natta during this week will commence the building of the headwalls in the green swathe south of Brunswick road, there was a delay in the vegetation clearance last week which caused this delay.   Foremost will be carrying out vegetation clearance in multiple areas within the Mindenhurst development.   Soil- fix are working in the…

Details

Site Works Update – W/C 4th March 2019

Soil-fix are working to remove contamination from the Cala homes southern boundary and the green swathe, along with vegetation clearance. Natta are commencing the installation of the two headwalls on the northern end of the green swathe surface water drain. Mindenhurst road phase 3 and 4 is ongoing and has experienced a few issues that…

Details

Site Works Update – W/C 25th February 2019

The road upgrades to the Maultway are ongoing. There have been extra operatives placed to identify the build-up of traffic and change the traffic light phasing. Phase 3 & 4 of Mindenhurst road is ongoing and due for completion on May 19. The Mindenhurst branded site hoarding will be erected this week in front of…

Details