Site Works Update – W/C 13th August 2018

Severn Trent water services are completing their works to the frith houses and the other diversions. This will allow for the decommission and disconnection of the water main in Brunswick road   The southern fork to Brunswick road is now open and the northern fork closed. There are temporary traffic lights in this area to…

Details

Site Works Forecast

W/C 20th August Bat survey at the 25m range and RTF Mindenhurst road phase 3 & 4 Brunswick road drainage Brunswick road lighting columns BT exchange at the end of Brunswick are cutting trees on their boundary UKPS laying LV cables W/C 27th August Mindenhurst road phase 3 & 4 Brunswick road with traffic management…

Details

Site Works Update – W/C 6th August 2018

The southern fork of Brunswick road/Deepcut bridge road is currently being re-instated with tarmac to then allow for the closure of the northern fork. Continuing works further along Brunswick road to install storm drainage and road gullies.   South east water are making connections for the church and the church hall on Deepcut Bridge road…

Details

Site Works Update – W/C 30th July 2018

UKPS are drilling deeper boreholes at the two substation locations to achieve the required earthing readings.   Both phases of the spine road (Mindenhurst road) are progressing as planned. Utilities are being laid and some of the lighting columns will follow on.   In Brunswick road the works are progressing. The southern fork will be…

Details

Site Works Update – W/C 23rd July 2018

The new gas meter for Princess Royal Barracks has arrived onsite and is being installed. Once complete, southern gas networks will complete the process and divert the pipe work to allow the new road to be constructed.   Mindenhurst road (spine road) phase 3 & 4.   Drainage on Brunswick road is ongoing and for…

Details

Site Works Update – W/C 16th July 2018

Brunswick road works storm drainage in ongoing and progressing well, this will by the end of this week near the main gate to princess royal barracks. A full lane closure with temporary traffic signals will be in place.   Mindenhurst road construction on both phases. In phase 4 the laying of the new kerb line…