Site Works Update – W/C 10th December 2018

Brunswick road work is progressing well, with further layers of tarmac laid. Mindenhurst road phase 3 & 4 is ongoing. Maultway road upgrade works which includes traffic management, possible delays to in this area at peak times. To access Princess Royal barracks follow the diversion signs, this will take you to the Royal way gate.…

Details

Site Works Forecast

W/C 17th December Severn Trent water disconnection Resurfacing of the Haul road Brunswick road works Maultway road upgrades Mindenhurst road works Princess Royal barracks diversion Natta weekend working EOD survey & clearance Please note: The site will be closed and all works will cease from 22nd December until 2nd January 2019. From 1st December 2018…

Details

Site Works Update – W/C 3rd December 2018

At the haul road, near the officer’s mess, a team will be carrying out preparation work to be ready for some resurfacing work to take place.   The Mindenhurst road phase 3 & 4 (spine road) works is ongoing and progressing as planned.   Natta will be working on Saturdays up until the Christmas break.…

Details

Site Works Update – W/C 26th November 2018

The works on Brunswick road are ongoing and progressing well as planned, the new kerb lines are now installed and the road is almost ready for surfacing. Please note: to access Princess Royal Barracks please continue to follow the diversion that is in place which will direct all to the Royal way gate. Part of…

Details

Site Works Update – W/C 5th November 2018

Construction of Phase 3 & 4 Mindenhurst road is progressing as planned and in some sections we now have the base levels of tarmac laid.   The road closure to Brunswick road is still in place with a diversion taking you to the royal way gate to access Princess Royal Barracks. The construction works that…

Details

Site Works Update – W/C 15th October 2018

Tree clearance at the maultway is still ongoing, however, these works should be complete this week. BT will be at the maultway removing a number of the poles that will eventually be re-sited.   The Brunswick road closure and diversion has now been in place for nearly two weeks with minimal disruption to the day…

Details