Site Works Update – W/C 29th July 2019

Hydrock are continuing their ground investigation surveys across the whole site for all phases of work. Keltbray are continuing the works in the green swathe and are aiming to complete this week. The village green works are progressing as planned, with the soft landscaping commencing this week. The offline drainage within Princess Royal Barracks is…

Details

Site Works Update – W/C 22nd July 2019

Hydrock are still carrying out ground investigation surveys across the whole site for all phases of work, some of these will be within the confines of Princess royal barracks. Keltbray are continuing the works in the green swathe with completion due in the early part of next week. The village green works are ongoing with…

Details

Site Works Update – W/C 15th July 2019

Village green works are continuing as planned and making progress. The works to Deepcut bridge road Rail Bridge are ongoing. The bridge has been closed to for all access and there is a traffic diversion in place. The Mindenhurst road construction is ongoing, site hoarding for the school and other land parcels are being installed…

Details

Site Works Update – W/C 8th July 2019

Village green works are ongoing. The works to Deepcut bridge road Rail Bridge are ongoing. The bridge has been closed to for all access and there is a traffic diversion in place. The Mindenhurst road construction is ongoing and nearing completion. Frimley lock and Frith Hill footpath works are ongoing and making good progress. Hydrock…

Details

Site Works Update – W/C 24th June 2019

Village green works are ongoing. The works to Deepcut bridge road Rail Bridge are ongoing. The bridge has been closed to for all access and there is a traffic diversion in place. The Mindenhurst road construction is ongoing and nearing completion. Frimley lock and Frith Hill footpath works are ongoing and making good progress. Hydrock…

Details