Site Works Update – W/C 11th March 2019

Natta during this week will commence the building of the headwalls in the green swathe south of Brunswick road, there was a delay in the vegetation clearance last week which caused this delay.   Foremost will be carrying out vegetation clearance in multiple areas within the Mindenhurst development.   Soil- fix are working in the…

Details

Village Green Public Notice

Additional works are due to take place on the village green. These works include replacing the planting and top soil on the village green and are due to be complete by the end of May 2019. Public access will then be available for people to enjoy the pathways and play equipment, with access temporarily restricted…

Details

Site Works Update – W/C 4th March 2019

Soil-fix are working to remove contamination from the Cala homes southern boundary and the green swathe, along with vegetation clearance. Natta are commencing the installation of the two headwalls on the northern end of the green swathe surface water drain. Mindenhurst road phase 3 and 4 is ongoing and has experienced a few issues that…

Details

Site Works Update – W/C 25th February 2019

The road upgrades to the Maultway are ongoing. There have been extra operatives placed to identify the build-up of traffic and change the traffic light phasing. Phase 3 & 4 of Mindenhurst road is ongoing and due for completion on May 19. The Mindenhurst branded site hoarding will be erected this week in front of…

Details

The Maultway Roundabout

As part of Surrey County Council’s road improvement plans, Skanska has been asked to enlarge the roundabout that junctions the Maultway and Red Road. This update will accommodate the increased traffic flow through the area and will ensure that the future population of Mindenhurst will not impact the traffic flow through the area. When the…

Details