Site Works Update – W/C 29th July 2019

Hydrock are continuing their ground investigation surveys across the whole site for all phases of work. Keltbray are continuing the works in the green swathe and are aiming to complete this week. The village green works are progressing as planned, with the soft landscaping commencing this week. The offline drainage within Princess Royal Barracks is…

Site Works Update – W/C 22nd July 2019

Hydrock are still carrying out ground investigation surveys across the whole site for all phases of work, some of these will be within the confines of Princess royal barracks. Keltbray are continuing the works in the green swathe with completion due in the early part of next week. The village green works are ongoing with…