Site Works Update – W/C 16th April 2018

The pond decking at the village green has significantly with the decking around the pond nearing completion and the play area in a similar position.   Excavations are under way around the Minden 2/9 substation in preparation for the decommissioning of the equipment and diversion of cables.   Brunswick road deep drainage is progressing well…

Site Works Forecast

  W/C 23rd April – Mindenhurst school fence – Village green – Central SANGS footpaths – Brunswick road works – Pump house construction – SANGS car park construction – Spine road construction W/C 30th April – Village green – Spine road construction – Power outages 1st May will involve power disruptions to Newfoundland Road MQ /…