Site Works Update Week 47

Construction of the central SANGs commenced on Thursday 23rd November within the woodland north of Princess Royal Barracks. These works will see the creation of new footpaths and make this area more accessible. The construction of footpaths will commence on Monday 4th December using small plant machinery. This area will include a small car park off the Royal Way with a wardens hut. Dogs should be kept on the lead in this area during construction.

Site Works Update Week 46

Construction of the central SNAGS (woodland area North of Princess Royal Barracks ) commenced on Thursday 23rd November 2017. These works will create new footpaths through the woodland, increasing accessibility, and provision of car parking. Initial activities include 7 days of vegetation clearance followed by path construction – Please keep dogs on a lead in this area.