Village Green Public Notice

Additional works are due to take place on the village green. These works include replacing the planting and top soil on the village green and are due to be complete by the end of May 2019. Public access will then be available for people to enjoy the pathways and play equipment, with access temporarily restricted…

Site Works Update – W/C 4th March 2019

Soil-fix are working to remove contamination from the Cala homes southern boundary and the green swathe, along with vegetation clearance. Natta are commencing the installation of the two headwalls on the northern end of the green swathe surface water drain. Mindenhurst road phase 3 and 4 is ongoing and has experienced a few issues that…